| PM 4: Detailed Planning |
Contents
|
|
|
|---|
Product Flow
| From | Product | to | Methods | Tool Req. | Ext. Norms | |||
|---|---|---|---|---|---|---|---|---|
| Activity | State | Chapter | Title | Activity | State | |||
| SD2 | being proc./ accepted |
All | System Architecture | - | - |
/ISO IEC 12207/
Supply Proc.: Devlp. Proc.: Doc. Proc.: Mngmt. Proc.: Infraest. Proc.: Training Proc.: |
||
| PM1 | accepted | All | Project Manual | - | - | |||
| PM3 PM6 PM8 |
- | All | Report Documents: Protocol Progress Report Final Project Report Case Report Memo Internal Message Invitation |
- | - | |||
| - | - | All | Product | CM2 | planned | |||
| PM1 | being proc. | All | Project Plan | PM3 PM4 PM6 PM7 PM8 PM10 PM11 PM12 PM14 CM4 |
being proc. (1) |
BAR (2) EMOD NPT (2) TREE |
SPM01 SPM04 SPM05 |
|
+ "Chapter" are extra columns from the original printed version of GD 250
Handling
Detailed planning requires the following steps:
This activity must be carried out prior to the realization of an activity or the generation of a product.
For this, all technical deletion conditions contained in the Project Manual, chapter Overview, are applied to the activity under discussion or to the product. If the condition with regard to an activity or product has been fulfilled the corresponding activity/product or product chapter may be dropped.
Activities or products for which no technical deletion conditions have been defined or for which deletion conditions have not been fulfilled must be realized or generated, respectively.
When generating a product it must be observed that for chapters for which respective deletion conditions have been fulfilled and which can therefore be dropped, the chapter headings and the chapter numbers shall be kept. The reason for deleting the chapter will then replace the chapter text.
Concerning activities of the next planning section, it must be decided who will take over which tasks-and when-and which dependencies among them will exist (process organization). CM and PM activities are only planned, if the general information laid down in the CM Plan or Project Manual are not sufficient. Planning of QA activities takes place in the Assessment Plan. As soon as new products are planned, they have to be passed on for configuration identification (the product is allocated the state "planned").
Depending on the experience of the risk management, the preliminary planning must be modified.
Recommendation
Explanation
Roles
| Role | Participation | ||
|---|---|---|---|
| Project Leader | responsible
| Project Administrator |
cooperating
| |
Methods
| Product | Methods Allocation | Use |
|---|---|---|
|
Chapter 2.1 Project Plan. Product Structure Plan |
TREE - Tree Diagram | Generate |
|
Chapter 2.2 Project Plan. Process Organization |
NPT - Network Planning Technique | Generate |
|
Chapter 3.1.1 Project Plan. Efforts (Planned and Actual) for SD/QA/CM/PM Activities |
EMOD - Estimation Models | Generate |
|
Chapter 3.1.2 Project Plan. Deadlines (Planned and Actual) for SD/QA/CM/PM Activities |
BAR - Bar Plan | Generate |
|
Chapter 3.1.3 Project Plan. Milestone Plan |
BAR - Bar Plan | Generate |
|
Chapter 3.1.6 Project Plan. Delivery and Supply Deadlines |
BAR - Bar Plan | Generate |
|
Chapter 3.2.1 Project Plan. Planned Values |
BAR - Bar Plan (2) | Generate |
| EMOD - Estimation Models | Generate | |
| NPT - Network Planning Technique (2) | Generate | |
|
Chapter 4.1 Project Plan. Staff |
BAR - Bar Plan | Generate |
|
Chapter 4.2 Project Plan. Resources |
BAR - Bar Plan | Generate |
Tools Requirements
External Norms
| Norm | Process | Chapter | Obs. |
|---|---|---|---|
| /ISO IEC 12207/ | Supply Process | Execution and Control | (s. Part 3 - ISO 3.2.1) |
| Development Process | Process Implementation | (s. Part 3 - ISO 3.2.1) | |
| Documentation Process | Process Implementation | (s. Part 3 - ISO 3.2.2) | |
| Management Process | Planning | (s. Part 3 - ISO 3.2.3) | |
| Infraestructure Process | Establishment of the Infraestructure | (s. Part 3 - ISO 3.2.3) | |
| Training Process | Process Implementation | (s. Part 3 - ISO 3.2.3) |
(2) Method BAR is to be applied if no complex arrangement relations and logical interdependences exist during the detailed planning; otherwise method NPT has to be applied.
![]() |
![]() |