| ISO.3.2.2 Supporting Processes |
ISO.3.2.2 Supporting Processes
The V-Model does not include any separate documentation activity. Documentation is basically not contained in the realization of activities. Therefore, the allocation of V-Model activities is not possible, even though the documentation process in the entire V-Model is naturally completely realized.
Apart from the configuration management and the change management of the V-Model, the Configuration Management process of the ISO 12207 standard also handles "Configuration Evaluation". There is no similar description in the V-Model.
According to ISO 12207, the Joint Review, Audit, Verification and Validation are handled as techniques of the process Quality Assurance. However, since the quality assurance process has only been roughly described, an explicit placement of these techniques is missing. Though the V-Model covers all of the listed QA aspects, a 1:1 allocation between V-Model and ISO 12207 is not always possible, based on the general information given in the ISO 12207 and the mixture between activities (tasks) and methods (techniques).
The V-Model always distinguishes between the activities process assessment, product assessment and phase review, and, on pages with method allocations, between audit, review (technical review and phase review), and testing, whereby the reason for applying a certain method depends on the objects tested (software, product, activity, project development).
Documentation Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
PM1.3 - Generation of Project-Specific V-Model
| PM1.5 - Generation of Preliminary Plan PM4 - Detailed Planning CM2.1 - Product Initialization Design and Development |
Product Schema
| QA4 - Product Assessment Production |
-
| Maintenance |
CM3 - Change Management (Configuration Control)
| | |
|---|---|---|---|---|---|---|---|---|---|---|---|
Configuration Management Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
CM1.1 - Generation the CM Plan
| Configuration Identification |
CM1.2 - Setting up CM
| CM2 - Product and Configuration Management Configuration Control |
CM3 - Change Management (Configuration Control)
| Configuration Status Accounting |
CM4.5 - Update of CM Documentation
| CM4.7 - Recording Project History Configuration Evaluation |
CM4.4 - Data Backup
| Release Management and Delivery |
CM4.6 - Release Management
| | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Quality Assurance Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
QA1.1 - Generation the QA Plan
| QA1.2 - Generation the Assessment Plan Product Assurance |
QA4.1 - Determination of Assessability
| QA4.2 - Assessment of the Content of the Product Process Assurance |
QA3 - Process Assessment of Activites
| Assurance of Quality Systems |
-
| | |
|---|---|---|---|---|---|---|---|---|---|---|---|
Verification Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
QA1.1 - Generation the QA Plan
| QA1.2 - Generation the Assessment Plan QA2.2 - Definition of Assessment Environment Verification |
QA2.1 - Definition of Assessment Methods and Criteria
| QA2.3 - Definition of Test Cases QA2.4 - Generation of Assessment Procedure QA3 - Process Assessment of Activites QA4.1 - Determination of Assessability QA4.2 - Assessment of the Content of the Product | |
|---|---|---|---|---|---|---|---|
Validation Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
QA1.1 - Generation the QA Plan
| QA1.2 - Generation the Assessment Plan QA2.2 - Definition of Assessment Environment Validation |
QA2.1 - Definition of Assessment Methods and Criteria
| QA2.3 - Definition of Test Cases QA2.4 - Generation of Assessment Procedure QA4.1 - Determination of Assessability QA4.2 - Assessment of the Content of the Product | |
|---|---|---|---|---|---|---|---|
Joint Review Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
QA1.1 - Generation the QA Plan
| Project Management Review |
PM6 - Phase Review
| Technical Review |
PM6 - Phase Review
| | |
|---|---|---|---|---|---|---|---|---|---|
Audit Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
QA1.1 - Generation the QA Plan
| Audit |
QA3 - Process Assessment of Activites
| QA4 - Product Assessment | |
|---|---|---|---|---|---|---|---|
Problem Resolution Process
| Activities according to ISO 12207 |
Activities according to the V-Model
| Process Implementation |
QA5 - QA Reporting
| Problem Resolution |
QA5 - QA Reporting
| CM4.7 - Recording Project History | |
|---|---|---|---|---|---|---|---|
![]() |
![]() |