QA2.1 - Definition of Assessment Methods and Criteria
| Assessment Specification of assessed object can be adopted from similar projects (same characteristics).
The assessment methods and criteria are specified by the customer. |
Product Assessment Specification comes from "outside".
 |
 |
QA2.2 - Definition of Assessment Environment
| Assessment environment can be adopted from similar project (same characteristics). |
The content of chapter Assessment Plan.Resources is specified. |
|
The assessed object is a document (i. e. unlike SW Module, Database, SW Component, SW Unit, Segment, or System). |
Chapter Assessment Plan.Resources is omitted. |
 |
 |
QA2.3 - Definition of Test Cases
| The assessed object is a document (i. e. unlike SW Module, Database, SW Component, SW Unit, Segment or System).
The assessed object is a SW Component, a SW Module or a Database; it has, however, no criticality and only few maintenance requirements. |
Chapter Assessment Specification.Test Cases is omitted.
 |
 |
QA2.4 - Generation of Assessment Procedure
| The assessed object is a document (i. e. unlike SW Module, Database, SW Component, SW Unit, Segment or System).
The assessment is computer aided so manual tasks are not required.
The assessment procedure is trivial.
The assessed object is a SW Component, a SW Module or a Database; it has, however, no criticality and only few maintenance requirements. |
Product Assessment Procedure is omitted.
 |
 |
QA3 - Process Assessment of Activites
| The project members are sufficiently familiar with the specified procedures and the V-model which have already been applied in earlier projects (deletion condition cannot be applied for Systems where security is a critical factor). |
-
|
| - |
- |
QA4 - Product Assessment |
|
|
 |
 |
QA4.1 - Determination of Assessability
| In the QA Plan, no assessment is planned for the assessed object (assessments are demanded for User Requirements, System Architecture, and System, though).
The determination of assessability is realized informally when the assessed subject is submitted. |
-
|
| - |
 |
QA4.2 - Assessment of the Content of the Product
| In the QA Plan, no assessment is planned for the assessed object (assessments are demanded for user requirements, System Architecture, and System, though). |
-
|
 |
 |
QA5 - QA Reporting
| The QA reporting is handled by the PM reporting. |
Activity PM9 - Information Service/Reporting must not be deleted.
| | | |