| PM 1.1: Setting up the Project |
Contents
|
|
|
|---|
Product Flow
| From | Product | to | Methods | Tool Req. | Ext. Norms | |||
|---|---|---|---|---|---|---|---|---|
| Activity | State | Chapter | Title | Activity | State | |||
| External | - | All | Project Order | - | - |
/ISO IEC 12207/
Acquis. Proc.:
Mngmt. Proc.: |
||
| - | - | 7 | Project Manual.Project Organization | PM1.3 | being proc. | OGC | SPM02 | |
+ "Chapter" are extra columns from the original printed version of GD 250
Handling
The availability of a project order is the required prerequisite for the realization of this activity; at least, it has to contain the following:
The decision-makers have to be appointed for all future decisions (procurement, placement of orders, etc.), depending on how important a decision is.
All results requiring an approval must be identified, and the corresponding instances for the approval have to be defined.
According to the (possibly contractual) requirements it is necessary to specify which reports must be generated for whom at what time. The report generation is realized in activity PM9 - Information Service/Reporting.
In case the system shall be evaluated while being supervised, the participants of the evaluation instance and of the BSI as certification instance must be considered as organizational marginal conditions.
Roles
| Role | Participation | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| Project Manager | advising
| Project Leader |
responsible
| Project Administrator |
cooperating
| Q Manager |
advising
| CM Manager |
advising
| |
Methods
| Product | Methods Allocation | Use |
|---|---|---|
|
Chapter 7.1 Project Manual. Organizational Structure |
OGC - Organizational Chart | Generate |
Tools Requirements
| Product | Functional Tools Requirements |
|---|---|
| Project Manual.Project Organization | SPM02 - Supporting Planning of the Project Organization |
External Norms
| Norm | Process | Chapter | Obs. |
|---|---|---|---|
| /ISO IEC 12207/ | Acquisition Process | Initiation | (s. Part 3 - ISO 3.2.1) |
| Management Process | Initiation and Scope Definition | (s. Part 3 - ISO 3.2.3) |
![]() |
![]() |
GDPA Online
Last Updated 01.Jan.2002
Updated by Webmaster
Last Revised 01.Jan.2002
Revised by Webmaster
![]() |