| SPM06 - Supporting Project Control and Steering |
LPM06 - Projektkontrolle und -steuerung unterstützen
1 Allocation to V-Model and Methods Allocation
CM4.7 - Recording Project History
Method
EVT - Earned Value Method
TRDA - Trend Analysis
2 Brief Characteristics
3 Requirements
3.1 Requirements for Interfaces
| SPM06.I.1 | Granularity | The exchange of control parameters with SWFM01 - Workflow Management is possible for individual closed function packages of the tool by means of a disclosed, documented interface. |
| SPM06.I.2 | Input interface to SPM04 - Supporting Planning of the Project Realization | It is possible to integrate project realization plans collected with SPM04 directly from the object management without further transformation for the project control and steering. |
| SPM06.I.3 | Input interface to SPM05 - Supporting Cost Estimation | It is possible to integrate cost estimations collected with SPM05 without further transformation directly from the object management for the project control and steering. |
3.2 Requirements for the Methods Support
| SPM06.M.1 | EVT - Earned Value Method | |
| SPM06.M.1.1 | Earned value diagram | It is possible to represent the development course of the monetary value for the actual performance, the actual cost, and the planned cost in form of an Earned Value Diagram. |
| SPM06.M.2 | TRDA - Trend Analysis | |
| SPM06.M.2.1 | Trend curves | |
| SPM06.M.2.1.1 | Effort | It is possible to generate trend curves with regard to effort. |
| SPM06.M.2.1.2 | Schedule | It is possible to generate trend curves with regard to schedule. |
3.3 Requirements for Functions
| SPM06.F.1 | Evaluations | Evaluations are possible for selectable sections from the database (e. g. referring to project, activity, resource). |
| SPM06.F.2 | Reports | |
| SPM06.F.2.1 | Layout | The report generator allows the definition of a uniform page layout. |
| SPM06.F.2.2 | Structure | It is possible to freely define the content of the reports. |
| SPM06.F.2.3 | Addressees | It is possible to generate reports from the database by taking into consideration the group of addressees. |
| SPM06.F.2.4 | Report period | It is possible to select a time window. A time window limits the report to one report period. |
| SPM06.F.3 | Statistic evaluations | |
| SPM06.F.3.1 | Evaluations per activity | It is possible to realize statistic evaluations with regard to activities. |
| SPM06.F.3.2 | Evaluations per resource | It is possible to realize statistic evaluations with regard to resources. |
| SPM06.F.3.3 | Evaluations per product | It is possible to realize statistic evaluations with regard to products. |
| SPM06.F.3.4 | Evaluations for the total project | It is possible to realize statistic evaluations with regard to the total project. |
| SPM06.F.3.5 | Evaluations for any time windows | It is possible to realize statistical evaluations for any time windows. |
| SPM06.F.4 | Comparing plans | It is possible to compare various plan versions. |
| SPM06.F.5 | Simulation | It is possible to simulate different scenarios. |
| SPM06.F.6 | Missed deadlines | It is possible to automatically display if deadlines have been missed. |
3.4 Other Requirements
| SPM06.O.1 | Experience database | It is possible to file planned and actual values in an experience database. |
| SPM06.O.2 | Upward compatibility | It must be possible to process objects generated with an older release of the tool with the later release of that tool, without loss of information and functionality. |
| SPM06.O.3 | Procedural command language | The tool has a procedural command language that can be applied by the user to generate and run macros or procedures. |
| SPM06.O.4 | Complexity | There is no limitation of the complexity caused by the tool itself. |
![]() |
![]() |